August 20266 min readBy Oraya Builders Team
Grey Structure Checklist: What to Check Before Every Roof Slab
Once the concrete is poured, mistakes are buried for good. Check these things on site before every roof slab is cast.

On this page
Why the Slab Day Matters
The roof slab is poured in one day, and after that you can't see the steel inside it. Most structural problems in houses start with something that was missed on slab day. Before you say "go ahead", check these points.
Steel
- Right size bars: Check the bar sizes match the structural drawing. Bars are usually marked with their size.
- Right spacing: Measure the gap between bars with a tape. It should match the drawing.
- Cover blocks: Small concrete blocks should lift the steel off the shuttering, so concrete can flow underneath. Steel lying directly on the shuttering will rust later.
- Clean steel: Light surface rust is fine. Flaky, heavy rust is not.
Shuttering
- Strong supports: The props holding up the shuttering should be straight, close together and resting on firm ground.
- No gaps: Gaps in the shuttering let the cement paste leak out, leaving weak, honeycombed concrete.
- Level: The shuttering should be level, with a slight slope where rainwater needs to drain.
Pipes and Fittings
- Electrical pipes: All ceiling light and fan points should be in place before the pour. Adding them later means breaking the slab.
- Plumbing sleeves: Pipes that pass through the slab need sleeves fixed now.
On the Day
- Concrete mix: Ask what mix is being used, and make sure it matches the drawing. Ready-mix concrete is more consistent than mixing on site.
- Test cubes: Samples of the concrete should be taken in cube moulds and sent to a lab. This proves the strength later.
- Vibrator: A concrete vibrator should be used to remove air pockets.
After the Pour
- Curing: The slab must be kept wet for at least 7 to 14 days. Ponding water on the roof is the simplest way.
- Props stay: Supports should stay in place for the time your engineer specifies, usually around 2 to 3 weeks.
Our engineers sign off every slab before concrete is poured, and you get photos of each check.