March 20266 min readBy Engr. Zeeshan Tariq, Head of Cost Estimates
House Construction Cost Per Sq. Ft. in Pakistan (2026)
Today's rates for steel, cement, bricks, labour and finishing, and what it costs to build on a 1,125 sq ft (5 Marla), 2,250 sq ft (10 Marla) or 4,500 sq ft (1 Kanal) plot in Lahore, Islamabad and Karachi.

On this page
Today's Material Prices
To plan your house budget, you need to know current material prices. In 2026, Grade 60 steel costs about PKR 265,000–270,000 per ton. Cement costs about PKR 1,450–1,500 per 50kg bag.
1. Grey Structure Rates (PKR 3,000 – 3,250 / sq. ft.)
Grey structure is the basic frame of the house:
- Digging & Foundations: Digging, anti-termite spray, a base layer of plain concrete, and steel-reinforced footings.
- Concrete Frame: Earthquake-safe columns, beams and roofs, poured with concrete of at least 3,000 PSI.
- Walls: First-class baked clay bricks laid in cement-sand mortar (1:4 and 1:6).
- Water Tanks: Underground and overhead concrete tanks with a waterproofing additive.
- Pipes: Electrical pipes inside the walls, and pressure-tested hot and cold PPRC water pipes.
2. Finishing Rates (PKR 4,500 – 8,000 / sq. ft.)
Finishing turns the grey structure into a home you can move into. It takes up about 65% of the total budget:
- Standard Finishing (PKR 4,500 - 6,000 / sq. ft.): Good local porcelain tiles (e.g. Master, Time Ceramic 60x60cm), semi-solid ash wood doors, branded bathroom fittings (Porta/IIL), emulsion paint, and glossy acrylic kitchens.
- Premium Finishing (PKR 6,100 - 8,000 / sq. ft.): Large imported Spanish/Italian tiles (120x120cm), solid carved ash/oak main doors, hidden flush tanks with Grohe/Kohler taps, LED strip lighting, and security sensors.
3. Typical Covered Area by Plot Size
- 1,125 sq ft (5 Marla) plot: 1,900 to 2,250 sq. ft. covered. Total cost about PKR 1.05 Cr to 1.25 Cr, fully finished.
- 2,250 sq ft (10 Marla) plot: 3,300 to 3,700 sq. ft. covered. Total cost about PKR 1.85 Cr to 2.25 Cr, fully finished.
- 4,500 sq ft (1 Kanal) plot: 5,400 to 6,200 sq. ft. covered. Total cost about PKR 3.0 Cr to 4.2 Cr, fully finished.
Always ask for a BOQ (cost breakdown) with a fixed rate for each item, not one lump-sum price. This protects you from price hikes halfway through the job.